Bridge #238 - Lakeshore Dr. East over Carmel Creek

Project Information


Current Status


09/14/16: Construction is nearly complete, and Lakeshore Drive is now open to traffic. 
A small amount of incidental work remains, but it will be completed under traffic.  Please proceed with caution through the work zone when workers are present.

flickr photo album

Project Location


Bridge #238 carries Lakeshore Drive East over Carmel Creek, located approximately 0.3 miles south of 106th Street just east of Keystone Pkwy.

Project Scope


The proposed scope of work includes widening the bridge to accommodate a new sidewalk on the east side, along with replacing the existing bridge deck and adjacent prestressed concrete box beams with a continuous reinforced concrete slab.  The existing railing on the bridge will be replaced with a new railing system that meets current design standards, and new reinforced concrete approach slabs will be added to each end of the bridge.  The existing piers will be repaired and riprap will be placed for scour protection.

Reason for Project


Reconstruction of the structure is necessary due to structural deterioration and inadequate roadway width.

Construction Details


  • Design Firm: HWC Engineering
  • Inspection Firm: Durham Engineering
  • Contractor: Duncan Robertson
  • Construction Start Date: June 2016
  • Construction Completion: September 30, 2016
  • Construction Cost: $600,000

Funding


Design and construction costs will be locally funded.

General Bridge Information 


  • Bridge Type: Prestressed Concrete Box Beam
  • Year Built: 1980
  • Structure Length: 74'
  • Average Daily Traffic:  2,060 (2013)

Bridge #238 - Lakeshore Dr. over Carmel Creek