Bridge #70 - 266th St. Over Bear Creek

Project Information

Current Status

October 30, 2015: Construction is complete.

Project Location

Bridge #70 carries 266th Street over Bear Creek in White River Township just west of Ray Parker Road.

Project Scope

Replacement of the existing bridge with a 3-span reinforced concrete slab with an overall length of 65 feet, and a clear roadway width of 32 feet.

Reason for Project

Replacement of the structure was necessary due to structural deterioration.

Construction Details

  • Design Firm: Butler, Fairman & Seufert
  • Contractor: Hoosier Pride Excavating 
  • Construction Start Date: May 2015
  • Construction Completion: September 2015
  • Construction Cost:  $409,000


The design and construction costs were be locally funded.