146th St. West - Phase 1

Project Information


Current Status


08/31/16: Phase 1 Construction is complete. Phase 2 Construction is expected to begin in the Fall of 2016.

Project Location


Spring Mill Rd. to Ditch Rd.

Project Scope


The road has been reconstructed to a 5-lane section with center median.

Construction Details

  • Design Firms: 
    • American Structurepoint
    • United Consulting Engineers
    • CHA - Phase 1
  • Contractor: E&B Paving (Phase 1)
  • Construction Start Date: August 2014 (Phase 1)
  • Construction Completion: Fall 2016 (Phase 1)
  • Construction Cost:  $6 million (Phase 1)

Funding


Design: Locally funded
Construction and Construction Inspection:
80% Federal Aid / 20% Local