Bridge 159 - Eller Rd. over Cheeney Creek 

Project Information


Current Status


October 12, 2015: Construction is complete. 

Project Location


Bridge #159 carries Eller Road over Cheeney Creek in Delaware Township just north of 106th Street.

Project Scope


Rehabilitation of the existing bridge to provide additional travel width and accommodate a future intersection improvement at 106th Street and Eller Road.

Construction Details


  • Design Firm: American Structurepoint
  • Contractor: Hoosier Pride Excavating
  • Construction Start Date: June 2015
  • Construction Completion: September 2015
  • Construction Cost: $464,000

Reason for Project


Rehabilitation of the structure is necessary due to inadequate width and substandard traffic safety features.


Funding


Design and construction costs will be funded by G.O. Bond.