146th St. Trails - Carey Rd. to Hazeldell pkwy.

Project Information


Current Status


09/07/16: Construction is complete. 

Project Location


Along 146th St. from .13 mi. east of Carey Rd. to .10 mi. west of Hazeldell Pkwy.

Project Scope


Construction of a new Multi-use Path.

Reason for Project


Added pedestrian connectivity between pre-existing sections of multi-use paths along 146th St.

Construction Details


  • Design Firm: Cripe Architects & Engineers
  • Inspection Firm:  First Group Engineering
  • Contractor: Calumet Civil Contractors
  • Construction Start Date: April 11, 2016
  • Construction Completion: September 3, 2016
  • Construction Cost:  $448,000

Funding


Design: Locally funded
Construction and Construction Inspection: 80% Federal Aid / 20% locally funded