Bridge #35 - 106th St. Over Williams Creek

Project Information

Current Status

09/03/2016: Construction is complete.

flickr photo album

Project Location

Bridge #35 carries 106th Street over Williams Creek in Clay Township just west of Springmill Road.

Project Scope

The project included the replacement of bridge superstructure with concrete beams.

Reason for Project

Rehabilitation of the structure was necessary due to structural deterioration, narrow width, and substandard roadside safety features.

Construction Details

  • Design Firm: Lochmueller Group
  • Inspection Firm: HWC Engineering
  • Contractor: HIS Constructors
  • Construction Start Date: May 16, 2016
  • Construction Completion: September 3, 2016
  • Construction Cost: $836,467


The design and construction costs were locally funded.
Bridge #35 - 106th St. over Williams Creek