Structure #23060 - Prairie Baptist Rd. Over Gwinn Ditch

Project Information

Current Status

10/14/16: Construction is underway. Prairie Baptist Rd. is closed between 191st St. & 206th St. for the duration of the project. The project is expected be complete before Novemeber 1st, at which time Prairie Baptist Rd. will be open to traffic.

flickr photo album

Project Location

Structure #23060 is located on Prairie Baptist Rd. between 191st St. and 206th St.

Reason for Project

Deterioration has occurred at various locations along the arch ring. Currently, the geometry of the structure is one-lane and has sight distance issues due to a rise on both sides of the structure.

Project Scope

The proposed design will widen the roadway and structure to two 12 foot lanes and a minimum 4-foot shoulder. The roadway will be elevated to eliminate any sight distance issues. The new structure will be able to accommodate a Q100 flood event with an additional two feet of free board for unexpected flood events.

Construction Details

  • Design Firm: HWC Engineering
  • Inspection Firm:  Hamilton County
  • Contractor: Hoosier Pride Excavating
  • Construction Start Date: June 14, 2016
  • Construction Completion: November 1, 2016
  • Construction Cost: $650,000 est.


Design and construction costs will be funded locally.

SS#23060 - Prairie Baptist Rd. over Gwinn Ditch