Structure #32059 - Cal Carson Rd. & Taylor Drain

Project Information

Current Status


05/18/17The construction contract has been awarded to Hoosier Pride Excavating. Construction is expected to begin on May 30th.

Project Location


Structure #32059 is located on Cal Carson Road, 500 feet north of 256th Street.
Google_StreetView

Reason for Project


Replacement of the structure is necessary due to the replacement of another structure nearby (SS#32028 - 256th St. over Taylor Drain).

Project Scope


Proposed design will widen the roadway and structure to 2 12-foot lanes and a minimum 4-foot shoulder. The new structure will also accommodate a Q100 flood event.

Construction Details


  • Design Firm: DLZ
  • Inspection Firm:  Hamilton County Highway Department
  • Contractor: Hoosier Pride Excavating
  • Construction Start Date: May 30, 2017
  • Construction Completion: September 2017
  • Project Cost: $622,222

Funding


The design and construction of this project will be funded using GO Bond proceeds