SS#33065 - Deer Walk Dr. over Webb Ditch

Project Information


Current Status


1/11/17: The construction contract has been awarded to Hoosier Pride Excavating

Project Location


The small structure is located on Deer Walk Dr. off of Joyce Ave. in White River Township.

Reason for Project
Deterioration has occurred at the joints and invert of the pipe.

Project Scope


Proposed design will keep the same roadway width and length. Structure will be able to accommodate a Q100 flood event.

Construction Details


  • Design Firm: Beam. Longest & Neff
  • Contractor: Hoosier Pride Excavating
  • Construction Start Date: March 2017
  • Construction Completion: late Summer 2017 est.
  • Construction Cost: $280,835* (does not include design or right-of-way costs)