Allisonville & Cumberland Intersection Improvement

Effective on or after March 20, 2017, clearing of Right-of-Way will begin at the intersection of Allisonville Road and Cumberland Road. The work is expected to take 7 days to complete. Temporary lane closures and traffic delays can be expected throughout the duration of the work.

Project Information


Current Status


03/16/17: Right-of-way clearing is underway. Construction is scheduled begin in June of this year.

flickr photo album

Project Location


The project will take place at the intersection of Allisonville Rd. and Cumberland Rd. in Fall Creek Township.

Project Scope


The improvement project will consist of a single-lane roundabout.

Reason for Project
Improvements are needed to improve traffic flow and reduce congestion.

Construction Details


  • Design Firm: USI Consultants
  • Inspection Firm: USI Consultants
  • Contractor: Calumet Civil Contractors, Inc.
  • Construction Start Date: June 2017
  • Construction Completion (Estimate): August 2017
  • Construction Cost: $830,000

Funding


Design costs will be locally funded. Construction will be funded 80% by Federal Aid / 20% local match.
Allisonville & Cumberland Roundabout