Bridge #238 - Lakeshore Dr. East over Carmel Creek

Project Information

Current Status

09/14/16: Construction is complete. 

flickr photo album

Project Location

Bridge #238 carries Lakeshore Drive East over Carmel Creek, located approximately 0.3 miles south of 106th Street just east of Keystone Pkwy.

Project Scope

The scope of work included widening the bridge to accommodate a new sidewalk on the east side, along with replacing the existing bridge deck and adjacent prestressed concrete box beams with a continuous reinforced concrete slab.  The existing railing on the bridge was replaced with a new railing system that meets current design standards, and new reinforced concrete approach slabs were added to each end of the bridge.  The existing piers were repaired and riprap was placed for scour protection.

Reason for Project

Reconstruction of the structure was necessary due to structural deterioration and inadequate roadway width.

Construction Details

  • Design Firm: HWC Engineering
  • Inspection Firm: Durham Engineering
  • Contractor: Duncan Robertson
  • Construction Start Date: June 2016
  • Construction Completion: September 30, 2016
  • Construction Cost: $600,000


Design and construction costs were locally funded.

General Bridge Information 

  • Bridge Type: Prestressed Concrete Box Beam
  • Year Built: 1980
  • Structure Length: 74'
  • Average Daily Traffic:  2,060 (2013)

Bridge #238 - Lakeshore Dr. over Carmel Creek