Project Information

Current Status

3/12/18: Phase 2 construction is ongoing. Traffic has now switched to the new alignment. Please drive through this section with caution as construction crews are still at work.

flickr photo album

Project Location

All Phases: 146th St. from Boone Co. to Spring Mill Rd.

Project Scope

The expansion of 146th Street will continue from west of Springmill Road to the Boone County Line. The road will be reconstructed to a 5-lane section with center median. 146th Street will be limited access with no drives or curb cuts allowed between mile points. Frontage roads will be utilized parallel to 146th Street to access homes / businesses. Roundabout intersections are planned at the mile points (ie. Eagle Creek Road, Shelborne Road, Towne Road, and Ditch Road).

Construction Details

  • Design Firms: 
    • American Structurepoint
    • United Consulting Engineers
    • CHA - Phase 1
    • Beam, Longest & Neff - Phase 2
    • USI Consultants - Phases 3 and 4
  • Contractor: E&B Paving (Phase 2)
  • Construction Start Date: July 2017 (Phase 2)
  • Construction Completion: Summer 2018 (Phase 2)
  • Construction Cost:  $6,376,300 (Phase 2)


The design and 20% of construction will be locally funded. 80% of the construction and construction inspection costs will be funded using Federal Aid.