146th St. Path - River to Herriman

Project Information


Current Status


07/05/17: Construction is effectively complete. 146th St. is no longer under lane restrictions.

Project Location


The new path was constructed along the north side of 146th St. from River Rd. to Herriman Blvd.

Project Scope


A new multi-use path (including compliant curb ramps at the intersections) was constructed along the north side of 146th St. from Herriman Blvd. to River Rd.

Reason for Project

The project was needed to complete connectivity and provide pedestrian access along 146th St.



Construction Details

  • Design Firm: Paul Cripe & Assoc.
  • Contractor: E&B Paving
  • Construction Start Date: April 11, 2017
  • Construction Completion: June 30, 2017
  • Construction Cost: $392,100

Funding


The project was funded by Federal Aid with a Local Match (80/20).