106th St. & Mollenkopf Rd. Intersection Improvement

Project Information


Current Status


6/12/2019: Right-of-way clearing is underway. Utility relocation is scheduled to take place over the summer months with construction beginning in late August.

Project Location


The project will take place at the intersection of 106th St. and Mollenkopf Rd. in Fall Creek Township.

Google_StreetView
Opens a New Window.
close carousel
close carousel

Project Scope


Intersection Improvements will consist of adding a left turn lane for westbound traffic and replacing the signal.

Reason for Project
Improvements are needed to improve traffic flow and reduce congestion.

Construction Details


  • Design Firm: A&F Engineering
  • Inspection Firm: TBD
  • Contractor: E&B Paving
  • Construction Start Date: August 2019
  • Construction Completion: October 2019
  • Construction Cost: TBD

Funding


Design costs will be locally funded. Construction will be funded 80% by Federal Aid / 20% local match.