Structures #33016 / #33017 - 256th St. over Deer Creek

Project Information


Current Status


10/4/21: The construction contract has been awarded to Hoosier Pride Construction. Construction is expected to start in the spring of 2022.

Project Location


Structures #33016 and #33017 are located on 256th St. over Deer Creek just west of State Road 213 in Jackson Township.


close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel

Reason for Project


The two small structures are within a close proximity of each other, and the necessity of the second structure will be evaluated during the design process. The existing geometry of both structures are two lanes with stone shoulders. Deterioration has occurred on both structures at various locations.

Project Scope


The proposed design will replace SS #33016 and eliminate SS #33017.  The new structure geometry shall be two 12-foot lanes, 4’ shoulders, will accommodate a Q100 flood event, and meet current design standards.

Construction Details


  • Design Firm: Hanson Engineering
  • Inspection Firm: Hamilton County Highway Department
  • Contractor: Hoosier Pride
  • Construction Start Date: Spring 2022
  • Construction Completion: Summer 2022
  • Construction Cost: $450,000

Funding


Local funding