Reason for Project
The structure has suffered section loss at various locations along the barrel and has a separated wingwall.
Project Scope
The proposed design will widen the roadway and shoulder. The new structure will be elevated and able to accommodate a 100-year flood event.
Construction Details
- Design Firm: Stephen J. Christian & Associates
- Inspection Firm: Hamilton County Highway Department
- Contractor: 3D Construction
- Construction Start Date: September 20, 2021
- Construction Completion: November 15, 2021
- Construction Cost: $307k
Funding
This project will be funded using revenue from the County Option Income Tax fund.