Bridge #106 - Little Chicago Rd. over Morse Reservoir

Project Information


Current Status


8/30/21: Preliminary Design is underway.

Project Location


Bridge 106 carries Little Chicago Rd. over Morse Reservoir. 
Google_StreetView

Reason for Project

The bridge deck and beams are deteriorated. A superstructure replacement is recommended.


Project Scope


Bridge Rehabilitation – The bridge deck and beams will be replaced. The bridge will be widened to the east to accommodate a new trail constructed by the City of Noblesville.

Construction Details


  • Design Firm: USI Consultants
  • Inspection Firm: TBD
  • Contractor: TBD
  • Construction Start Date: Spring 2025
  • Construction Completion: Summer 2025
  • Construction Cost: TBD
Funding
This project is being completed in conjunction with the City of Noblesville trail construction project. The project will utilize Federal and Local (Hamilton County and City of Noblesville) Funding.