Bridge #59 - Westfield Park Dr. over Grassy Branch

Project Information


Current Status


8/30/21: The construction contract was awarded to 3D Construction. Construction is expected to begin in December.

Project Location


Bridge 59 carries Westfield Park Dr. over Grassy Branch. 
Google_StreetView

Reason for Project

The existing structure is deteriorated.


Project Scope


Bridge Rehabilitation – The existing structure will be replaced with a more hydraulically efficient structure.

Construction Details


  • Design Firm: V3 Companies
  • Inspection Firm: City of Westfield
  • Contractor: 3D Construction
  • Construction Start Date: Winter 2021
  • Construction Completion: Summer 2022
  • Construction Cost: $795,000
Funding
This project is being completed in conjunction with the City of Westfield. The project will utilize Local (Hamilton County and City of Westfield) Funding.