Bridge #146 - 151st St. over Cool Creek

Project Information


Current Status


8/30/21: Final Design is underway.

Project Location


Bridge 146 carries 151st St. over Cool Creek. 
Google_StreetView

Reason for Project

The bridge deck is deteriorated, and a bridge deck overlay is recommended.


Project Scope


Bridge Rehabilitation – A new overlay will be installed over the bridge deck and the bridge will be widened to the south to accommodate a new trail constructed by the City of Westfield.

Construction Details


  • Design Firm: USI Consultants
  • Inspection Firm: TBD
  • Contractor: TBD
  • Construction Start Date: Fall 2022
  • Construction Completion: Spring 2023
  • Construction Cost: TBD
Funding
This project is being completed in conjunction with the City of Westfield. The project will utilize Local (Hamilton County and City of Westfield) Funding.