Neighborhoods Impacted Thorpe Creek & South Avalon 3-week work outlook• Start 2/6/23 & 2/6/23 Finish – Continue Tree Clearing • Start 2/7/23 & 2/7/23 Finish – Finish storm valley crossing Dr. • Start 2/8/23 & 2/21/23 Finish – Topsoil stripping work....