Date: May 5th, 2016
Contact: Chris Burt
Traffic Technician
(317) 773-7770, Fax: (317) 776-9814
E-mail: Chris.Burt@hamiltoncounty.in.gov
Temporary Lane Restrictions
Please be advised, on or after Monday, May 9th, 2016, Calumet will begin work to construct a multi-use path along the north side of 146th Street. This project will fill in the missing sections of multi-use path on the north side of 146th St. between Carey Rd. and Hazeldell Pkwy.
The project has two phases, Carey Rd. to Gray Rd. and Gray Rd. to Hazeldell Pkwy. The first phase will be functionally complete before the second phase starts. Daily construction hours of the lane closure will be from 8am – 5pm Monday – Friday, with advanced warning signage being in place. The project is expected to be substantially completed in the middle of August.
With at least one lane of travel being open at all times during this work, we ask that you please use extreme caution driving through the construction zone.